4.

Among the reasons for having checkpoints in the software process are

  1. the need to achieve a concurrence of stakeholders' expectations and perspectives

  2. the need to establish a consistent artifact baseline

  3. the need to identify risk conditions

 (a) II only  (b) II and III only  (c) I and II only  (d) I, II, and III

Correct answer is

(d)

Your score on this question is:

0.00

Feedback:

   See chapter 9, page 125 in the textbook.    

5.

What are some possible topics for a status assessment review?

  1. Design and coding standards

  2. Major risks

  3. Technical progress

 (a) II and III only  (b) I and II only  (c) I and III only  (d) I, II, and III

Correct answer is

(a)

Your score on this question is:

0.00

Feedback:

   See section 9.3, page 134 in the textbook.    

6.

The purpose of a major milestone is to ensure

  1. consistency among artifacts

  2. a proper level of detail in requirements understanding

  3. concurrence among stakeholders

 (a) I, II, and III  (b) I only  (c) II and III only  (d) I and II only

Correct answer is

(a)

Your score on this question is:

0.00

Feedback:

   See section 9.1, pages 127-8 in the textbook.    

7.

How is a major milestone captured?

 (a) With a release specification and description  (b) With a demonstration of a technical capability  (c) With a final product  (d) With an artifact baseline

Correct answer is

(b)

Your score on this question is:

0.00

Feedback:

   See chapter 9, page 126 in the textbook.    

8.

What are the three types of checkpoints in the software process?

 (a) Client acceptance tests, major milestones, and minor milestones  (b) Client acceptance tests, minor milestones, and status assessments  (c) Client acceptance tests, major milestones, and status assessments  (d) Major milestones, minor milestones, and status assessments

Correct answer is

(d)

Your score on this question is:

0.00

Feedback:

   See chapter 9, page 125 in the textbook.    

9.

Status assessments should be performed

 (a) at the end of each iteration  (b) at the end of each phase  (c) every time a problem is encountered  (d) at regular intervals

Correct answer is

(d)

Your score on this question is:

0.00

Feedback:

   See section 9.3, page 133 in the textbook.    

10.

What is true of the number of major milestones that should be performed?

 (a) There should be more than one for every phase, regardless of the type of project.  (b) There should be one for every phase.  (c) They should be performed whenever a stakeholder makes a request.  (d) There is no need for one for every phase, regardless of the type of project.

Correct answer is

(b)

What is a release description?

 (a) An artifact that contains the results of release baselines  (b) An artifact that contains the scope, plan, and objectives of release baselines  (c) An artifact that represents a user manual for the release  (d) An artifact that contains the evaluation criteria for a release

Correct answer is

(a)

Your score on this question is:

10.00

Feedback:

   See chapter 9, page 126, and Glossary, page 395 in the textbook.    

2.

What is true of the number of minor milestones that should be performed?

 (a) There should always be two for every iteration.  (b) They should be performed whenever a stakeholder makes a request.  (c) Usually they are not necessary.  (d) The number depends on the complexity of the project and the length of the iteration.

Correct answer is

(d)

Your score on this question is:

10.00

Feedback:

   See chapter 9, page 126, and section 9.2, page 132 in the textbook.    

3.

Which is the most important major milestone?

 (a) The transition from the elaboration phase to the construction phase  (b) The transition from the construction phase to the transition phase  (c) The transition from the transition phase into the next iteration  (d) The transition from the inception phase to the elaboration phase

Correct answer is

(a)

Your score on this question is:

0.00

Feedback:

   See chapter 9, page 125 in the textbook.    

4.

What is usually done at a major milestone meeting, in general?

 (a) Process assessment  (b) Project status  (c) Review of artifacts  (d) Subcontractor analysis

Correct answer is

(c)

Your score on this question is:

10.00

Feedback:

   See section 9.1, page 127 in the textbook.    

5.

The purpose of a major milestone is to ensure

  1. consistency among artifacts

  2. a proper level of detail in requirements understanding

  3. concurrence among stakeholders

 (a) I and II only  (b) I only  (c) I, II, and III  (d) II and III only

Correct answer is

(c)

Your score on this question is:

0.00

Feedback:

   See section 9.1, pages 127-8 in the textbook.    

6.

What are some possible topics for a status assessment review?

  1. Design and coding standards

  2. Major risks

  3. Technical progress

 (a) I and II only  (b) II and III only  (c) I and III only  (d) I, II, and III

Correct answer is

(b)

Your score on this question is:

10.00

Feedback:

   See section 9.3, page 134 in the textbook.    

7.

What is the main goal of the product release milestone?

 (a) To assess the readiness of the software to begin the transition to customer-user sites and to authorize the start of acceptance testing  (b) To present to all stakeholders a recommendation on how to proceed with development  (c) To demonstrate an executable architecture to all stakeholders  (d) To assess the completion of the software and its transition to the support organization, if any

Correct answer is

(d)

Your score on this question is:

10.00

Feedback:

   See section 9.1, page 132 in the textbook.    

8.

Status assessments should be performed

 (a) at the end of each iteration  (b) every time a problem is encountered  (c) at regular intervals  (d) at the end of each phase

Correct answer is

(c)

Your score on this question is:

10.00

Feedback:

   See section 9.3, page 133 in the textbook.    

9.

What is true about major milestones?

 (a) They are performed at the end of each phase.  (b) They are conducted in an informal way.  (c) They do not involve stakeholders.  (d) They are performed at the end of each iteration.

Correct answer is

(a)

Your score on this question is:

10.00

Feedback:

   See chapter 9, page 126 in the textbook.    

10.

Of all stakeholders involved in a software project, who would be mostly concerned with the interoperability of existing systems?

 (a) Developers  (b) Customers  (c) Maintainers  (d) Users

Correct answer is

(c)

The purpose of a major milestone is to ensure

  1. consistency among artifacts

  2. a proper level of detail in requirements understanding

  3. concurrence among stakeholders

 (a) II and III only  (b) I and II only  (c) I, II, and III  (d) I only

Correct answer is

(c)

Your score on this question is:

10.00

Feedback:

   See section 9.1, pages 127-8 in the textbook.    

2.

What is a release description?

 (a) An artifact that contains the evaluation criteria for a release  (b) An artifact that contains the results of release baselines  (c) An artifact that contains the scope, plan, and objectives of release baselines  (d) An artifact that represents a user manual for the release

You did not answer this question.

Correct answer is

(b)

Your score on this question is:

0.00

Feedback:

   See chapter 9, page 126, and Glossary, page 395 in the textbook.

3.

What is the main goal of the life-cycle architecture milestone?

 (a) To assess the completion of the software and its transition to the support organization, if any  (b) To present to all stakeholders a recommendation on how to proceed with development  (c) To demonstrate an executable architecture to all stakeholders  (d) To assess the readiness of the software to begin the transition to customer-user sites and to authorize the start of acceptance testing

Correct answer is

(c)

Your score on this question is:

0.00

Feedback:

   See section 9.1, page 129 in the textbook.    